As we move in to week 3 of the Tomahawk North 4th Street project, Public Works director Mike Tolvstad provided an update on last week’s work.

He says they are now approaching the half-way point in the underground portion of the project.

All of the water main is installed and has passed necessary tests. Outside of a few catch basins, the majority of the storm sewer is also installed. The contractor hopes to complete the underground portion at some point next week.

The crews will not work on the 4th, but construction will resume on Friday the 5th and Saturday. Tolvstad also noted that they will not have the regular Thursday construction meeting due to the holiday.